Announcement of Bid Rejection
One Project Name: Bidding for Photovoltaic Power Generation Project of Hunan Chunguang Jiuhui Modern Traditional Chinese Medicine Co., Ltd.
II Project situation: The project was tendered online on November 21, 2022, and the deadline for bid opening is 9:30 am on November 30, 2022. A total of three units participated in the bidding.
III Reason for project rejection:
The winning bidder of this project, Hunan Xiangtou Power Sales Co., Ltd., quoted a total installed capacity of 2MW. However, after on-site investigation, it was found that only 1.4MW of power generation could be achieved, which is far from the estimated 2MW power generation in the bid; And issue a notification letter on March 13, 2023 regarding the capacity adjustment of the Chunguang Jiuhui distributed photovoltaic project. Due to significant differences in the specific implementation design capacity, it is suggested that this bidding be cancelled.
-
2025-04-15
Bidding announcement for the steam pipeline project of the old extraction and preparation workshop of Hunan Chunguang Jiuhui Modern Traditional Chinese Medicine Co., Ltd
-
2025-04-10
Announcement of Candidates for the Winning Bidder of the Chunguang Jiuhui Solid Waste Disposal Project
-
2025-03-31
Announcement on the postponement of the solid waste disposal project of Hunan Chunguang Jiuhui Modern Traditional Chinese Medicine Co., Ltd
Back